webvic-b

Altaaqa installs temporary power plant in Oman

Altaaqas temporary power plant will ensure peak performance during the hottest months of the year. (Image source: Altaaqa)

Power solutions provider Altaaqa Global CAT Rental Power has designed and installed a 24MW temporary power plant within a span of 96 hours in Oman

To meet electricity demands throughout the summer, the 24MW temporary rental power plant will supply power to the electricity grid at a time when there is a significant increase in the use of temperature control equipment, such as air conditioning and district cooling.

The power plant will ensure peak performance during the hottest months of the year supporting the existing generating capacity of Oman.

Altaaqa Global general manager for business development Peter den Boogert said, ?This reaffirms Altaaqa Global?s ability to install, commission and safely generate power within a matter of days. The full turnkey solution offers a complete package of power generators, transformers, fuel tanks, distribution panels, electrical accessories and 24/7 CAT certified power engineers who will manage the temporary power plant.?

Altaaqa Global managing director Steven Meyrick said, ?We are proud to deliver our temporary power solution to the people of Oman.

?Our rental power team and Caterpillar?s power dense and fuel efficient rental diesel generators is the perfect combination to provide grid optimisation and dependable supplementary power.?